Construction Engineering and Management

7 papers · 101602

2023101602

B.Tech 6th Semester Exam-2023

03 Hours70 marks

Instructions

  • The marks are indicated in the right-hand margin.
  • There are NINE questions in this paper.
  • Attempt FIVE questions in all.
  • Question No. 1 is compulsory.
  • Symbols used (if any) have their usual meanings.

Q.1 Answer any seven question of the following:

Ask AI
  1. Q1.1

    An activity is

    a)

    The beginning or end of a specified job

    b)

    An element of work entailed in the project

    c)

    The movement of heavy vehicle from one place to another

    d)

    The progress of work upto a certain limit

    Ask AI
  2. Q1.2

    The probabilistic time is given by (Where $ t_o = $ optimistic time, $ t_p = $ pessimistic time and, $ t_n = $ Most likely time)

    a)

    (to+tp+tn)/3(t_o + t_p + t_n)/3

    b)

    (to+2tp+tn)/4(t_o + 2t_p + t_n)/4

    c)

    (to+4tp+tn)/5(t_o + 4t_p + t_n)/5

    d)

    (to+4tn+tp)/6(t_o + 4t_n + t_p)/6

    Ask AI
  3. Q1.3

    Pert requires

    a)

    Single time estimate

    b)

    Double time estimate

    c)

    Triple time estimate

    d)

    None of these

    Ask AI
  4. Q1.4

    Which of the following is a dummy activity?

    a)

    Excavation foundation

    b)

    Laying the foundation concrete

    c)

    Awaiting the arrival of concrete material

    d)

    Curing the foundation concrete

    Ask AI
  5. Q1.5

    A Gantt chart indicates

    a)

    Balance of work to be done

    b)

    Efficiency of project work

    c)

    Comparison of actual process with the scheduled progress

    d)

    Progress cost of project

    Ask AI
  6. Q1.6

    Negative slack occurs

    a)

    When latest allowable time is greater than earliest expected time

    b)

    When events stick to their schedule

    c)

    When deficiency of resource exist

    d)

    None of these

    Ask AI
  7. Q1.7

    PERT calculation yield a project length of 60 week with a variance of 9 week. Probability factor corresponding to 95% is 1.647; then the number of week required to complete the project with a probability of 95% is

    a)

    60.94

    b)

    62.94

    c)

    64.94

    d)

    66.9417

    Ask AI
  8. Q1.8

    Which of the following earth moving machines has the shortest cycle time

    a)

    Drag line

    b)

    Hoe

    c)

    Clam shell

    d)

    Dipper shovel

    Ask AI
  9. Q1.9

    Which of the following data is not required to prepare an estimate?

    a)

    Amplitude

    b)

    Drawings

    c)

    Specifications

    d)

    Rates

    Ask AI
  10. Q1.10

    Force majeure can be

    a)

    Act of god

    b)

    Fire on explosion

    c)

    Wars on hostilities

    d)

    All of the above

    Ask AI

Q.2 Solve both questions :

Ask AI
  1. Q2.1

    (a) Describe various phases of project management.

    Ask AI
  2. Q2.2

    (b) Discuss in brief the basics of slip forming for tall structure.

    Ask AI

Q.3 Solve this question :

Ask AI
  1. Q3.1

    Following table shows details of activities of a small project: (i) Prepare AON network (ii) Prepare AOA network (iii) Identify critical path and duration of project (iv) Work out total, Free and independent floats

    Sr. No Activity Preceding Activity Cost per day (Rs. Thousand) Duration
    1 A - 5 14
    2 B - 6 10
    3 C - 4 20
    4 D A 8 10
    5 E B 4 160
    6 F C 3 12
    7 G D 3 10
    8 H D 5 8
    9 I E, F 4 20
    10 J G 2 10
    11 K H 3 16
    12 L I 3 18
    Ask AI

Q.4 Solve both questions :

Ask AI
  1. Q4.1

    Explain the application of BIM in project management. What are the safety measures to be considered in the construction site?

    Ask AI
  2. Q4.2

    A target date of completion is to be forecast based on the following information: Item A take 7 weeks for completion; Item B takes 5 weeks; Item C depend on the completion of both A and B, and requires 3 weeks; Item D follow up of item C and requires 2 weeks. Prepare a Gantt chart for scheduling the completion date.

    Ask AI

Q.5 Solve both questions :

Ask AI
  1. Q5.1

    (a) Compare and contrast CPM and PERT. Under what circumstance would you use PERT as opposed to CPM in project management?

    Ask AI
  2. Q5.2

    (b) Discuss the objectives of network analysis.

    Ask AI

Q.6 Solve both questions :

Ask AI
  1. Q6.1

    (a) What are the factors must be taken into account before selection of construction equipment.

    Ask AI
  2. Q6.2

    (b) calculate the output per day of a concrete mixture of 200 litres. Assume all data reasonably for the purpose.

    Ask AI

Q.7 Solve both questions :

Ask AI
  1. Q7.1

    (a) Discuss various rules for providing dummies in a network. What are redundant dummies?

    Ask AI
  2. Q7.2

    (b) What are the methods used for manufacture of precast concrete elements? Explain briefly

    Ask AI

Q.8 Solve both questions :

Ask AI
  1. Q8.1

    (a) Explain duties and responsibilities of parties involved in a contract.

    Ask AI
  2. Q8.2

    (b) Differentiate between conventional and mechanized methods of construction.

    Ask AI

Q.9 Write short notes on any four of the following:

Ask AI
  1. Q9.1

    a)

    Clam shell

    b)

    Modular construction

    c)

    Precast concrete construction

    d)

    Dewatering equipments

    e)

    Resource aggression and allocation

    f)

    Checklist for quality control

    Ask AI

2023V4101602

B.Tech 6th Semester Exam-2023

03 Hours70 marks

Instructions

  • The marks are indicated in the right-hand margin.
  • There are NINE questions in this paper.
  • Attempt FIVE questions in all.
  • Question No. 1 is compulsory.
  • Symbols used (if any) have their usual meanings.

Q.1 Answer any seven question of the following:

Ask AI
  1. Q1.1

    An activity is

    a)

    The beginning or end of a specified job

    b)

    An element of work entailed in the project

    c)

    The movement of heavy vehicle from one place to another

    d)

    The progress of work upto a certain limit

    Ask AI
  2. Q1.2

    The probabilistic time is given by (Where $ t_o = $ optimistic time, $ t_p = $ pessimistic time and, $ t_n = $ Most likely time)

    a)

    (to+tp+tn)/3(t_o + t_p + t_n)/3

    b)

    (to+2tp+tn)/4(t_o + 2t_p + t_n)/4

    c)

    (to+4tp+tn)/5(t_o + 4t_p + t_n)/5

    d)

    (to+4tn+tp)/6(t_o + 4t_n + t_p)/6

    Ask AI
  3. Q1.3

    Pert requires

    a)

    Single time estimate

    b)

    Double time estimate

    c)

    Triple time estimate

    d)

    None of these

    Ask AI
  4. Q1.4

    Which of the following is a dummy activity?

    a)

    Excavation foundation

    b)

    Laying the foundation concrete

    c)

    Awaiting the arrival of concrete material

    d)

    Curing the foundation concrete

    Ask AI
  5. Q1.5

    A Gantt chart indicates

    a)

    Balance of work to be done

    b)

    Efficiency of project work

    c)

    Comparison of actual process with the scheduled progress

    d)

    Progress cost of project

    Ask AI
  6. Q1.6

    Negative slack occurs

    a)

    When latest allowable time is greater than earliest expected time

    b)

    When events stick to their schedule

    c)

    When deficiency of resource exist

    d)

    None of these

    Ask AI
  7. Q1.7

    PERT calculation yield a project length of 60 week with a variance of 9 week. Probability factor corresponding to 95% is 1.647; then the number of week required to complete the project with a probability of 95% is

    a)

    60.94

    b)

    62.94

    c)

    64.94

    d)

    66.9417

    Ask AI
  8. Q1.8

    Which of the following earth moving machines has the shortest cycle time

    a)

    Drag line

    b)

    Hoe

    c)

    Clam shell

    d)

    Dipper shovel

    Ask AI
  9. Q1.9

    Which of the following data is not required to prepare an estimate?

    a)

    Amplitude

    b)

    Drawings

    c)

    Specifications

    d)

    Rates

    Ask AI
  10. Q1.10

    Force majeure can be

    a)

    Act of god

    b)

    Fire on explosion

    c)

    Wars on hostilities

    d)

    All of the above

    Ask AI

Q.2 Solve both questions :

Ask AI
  1. Q2.1

    (a) Describe various phases of project management.

    Ask AI
  2. Q2.2

    (b) Discuss in brief the basics of slip forming for tall structure.

    Ask AI

Q.3 Solve this question :

Ask AI
  1. Q3.1

    Following table shows details of activities of a small project: (i) Prepare AON network (ii) Prepare AOA network (iii) Identify critical path and duration of project (iv) Work out total, Free and independent floats

    Sr. No Activity Preceding Activity Cost per day (Rs. Thousand) Duration
    1 A - 5 14
    2 B - 6 10
    3 C - 4 20
    4 D A 8 10
    5 E B 4 160
    6 F C 3 12
    7 G D 3 10
    8 H D 5 8
    9 I E, F 4 20
    10 J G 2 10
    11 K H 3 16
    12 L I 3 18
    Ask AI

Q.4 Solve both questions :

Ask AI
  1. Q4.1

    Explain the application of BIM in project management. What are the safety measures to be considered in the construction site?

    Ask AI
  2. Q4.2

    A target date of completion is to be forecast based on the following information: Item A take 7 weeks for completion; Item B takes 5 weeks; Item C depend on the completion of both A and B, and requires 3 weeks; Item D follow up of item C and requires 2 weeks. Prepare a Gantt chart for scheduling the completion date.

    Ask AI

Q.5 Solve both questions :

Ask AI
  1. Q5.1

    (a) Compare and contrast CPM and PERT. Under what circumstance would you use PERT as opposed to CPM in project management?

    Ask AI
  2. Q5.2

    (b) Discuss the objectives of network analysis.

    Ask AI

Q.6 Solve both questions :

Ask AI
  1. Q6.1

    (a) What are the factors must be taken into account before selection of construction equipment.

    Ask AI
  2. Q6.2

    (b) calculate the output per day of a concrete mixture of 200 litres. Assume all data reasonably for the purpose.

    Ask AI

Q.7 Solve both questions :

Ask AI
  1. Q7.1

    (a) Discuss various rules for providing dummies in a network. What are redundant dummies?

    Ask AI
  2. Q7.2

    (b) What are the methods used for manufacture of precast concrete elements? Explain briefly

    Ask AI

Q.8 Solve both questions :

Ask AI
  1. Q8.1

    (a) Explain duties and responsibilities of parties involved in a contract.

    Ask AI
  2. Q8.2

    (b) Differentiate between conventional and mechanized methods of construction.

    Ask AI

Q.9 Write short notes on any four of the following:

Ask AI

2022101602

B.Tech 6th Semester Exam., 2022

03 Hours70 marks

Instructions

  • The marks are indicated in the right-hand margin.
  • There are NINE questions in this paper.
  • Attempt FIVE questions in all.
  • Question No. 1 is compulsory.
  • Assume any data not given.

Q.1 Choose the correct answer of the following (any seven):

Ask AI
  1. Q1.1

    For establishing and maintaining priorities among the various jobs of a project, the technique is known as

    a)

    critical ratio scheduling

    b)

    event flow scheduling technique

    c)

    slotting technique for scheduling

    d)

    short interval scheduling

    Ask AI
  2. Q1.2

    In case of CPM, the performance of a specific task is known as

    a)

    dummy

    b)

    event

    c)

    contract

    d)

    activity

    Ask AI
  3. Q1.3

    Military organization is also called as

    a)

    line organization

    b)

    line and staff organization

    c)

    functional organization

    d)

    None of the above

    Ask AI
  4. Q1.4

    Which of the following is incorrect statement?

    a)

    The activity is the time consuming part of a project.

    b)

    The beginning and end of a job, are called events.

    c)

    The activity which consumes maximum time, is called a node.

    d)

    Logically and sequentially connected activities and events form a network.

    Ask AI
  5. Q1.5

    Without affecting the start of succeeding activities, the time by which activity completion time can be delayed, is known as

    a)

    duration

    b)

    interfering float

    c)

    free float

    d)

    total float

    Ask AI
  6. Q1.6

    In bar chart, the various activities of a project, are shown by

    a)

    vertical lines

    b)

    horizontal lines

    c)

    dots

    d)

    crosses

    Ask AI
  7. Q1.7

    The time which is responsible for least possible construction cost of an activity, is

    a)

    normal time

    b)

    crash time

    c)

    standard time

    d)

    slow time

    Ask AI
  8. Q1.8

    If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively

    a)

    3.5 and (5/6)(5/6)

    b)

    5 and (25/36)(25/36)

    c)

    3.5 and (25/36)(25/36)

    d)

    4 and (5/6)(5/6)

    Ask AI
  9. Q1.9

    A critical ratio scheduling

    a)

    determines the status of each activity

    b)

    adjusts automatically changes in activity progress

    c)

    is a dynamic system

    d)

    None of the above

    Ask AI
  10. Q1.10

    A machine costs 20,000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be

    a)

    1,740

    b)

    3,480

    c)

    5,220

    d)

    6,960

    Ask AI

Q.2 Solve both questions :

Ask AI
  1. Q2.1

    Assess the present constructional infrastructure in India. Give the remedial measures keeping in mind the economic feasibility.

    Ask AI

Q.3 Solve this question :

Ask AI
  1. Q3.1

    What is critical path method? Prepare the network as per the data given in the Table 1 and compute in a table their early start, early finish, late start and late finish times. Determine the critical path and find the total float and free float for all the activities:

    Ask AI

Q.4 Solve both questions :

Ask AI
  1. Q4.1

    What do you mean by PERT and what is its significance?

    Ask AI

Q.5 Solve both questions :

Ask AI
  1. Q5.1

    Write the factors to be considered for precast concrete construction. What do you mean by scaffolding?

    Ask AI

Q.6 Solve this question :

Ask AI
  1. Q6.1

    Compare the characteristics and application of the different types of earth excavating equipment. Estimate the output of bulldozer for the following operating conditions: (a) Material - Sandy loam top soil (b) Swell - 25% (c) Haul distance - 45 m (d) Mould board size - 3.0 m long, 1.0 m high (e) Rated mould board capacity - 3 cu.m loose volume (f) Operating factor - 50 min/hr (g) Probable round trip time - 1.87 min.

    Ask AI

Q.7 Solve both questions :

Ask AI
  1. Q7.1

    Explain the application of BIM in project management. What are the safety measures to be considered in the construction site?

    Ask AI

Q.8 Solve both questions :

Ask AI
  1. Q8.1

    Explain the importance of organization in construction activities. What are the methods of scheduling?

    Ask AI

Q.9 Solve both questions :

Ask AI
  1. Q9.1

    What is called liquidated damage? What do you mean by direct cost and indirect cost?

    Ask AI

2022V2101602

B.Tech 6th Semester Exam., 2022

03 Hours70 marks

Instructions

  • The marks are indicated in the right-hand margin.
  • There are NINE questions in this paper.
  • Attempt FIVE questions in all.
  • Question No. 1 is compulsory.
  • Assume any data not given.

Q.1 Choose the correct answer of the following (any seven):

Ask AI
  1. Q1.1

    For establishing and maintaining priorities among the various jobs of a project, the technique is known as

    a)

    critical ratio scheduling

    b)

    event flow scheduling technique

    c)

    slotting technique for scheduling

    d)

    short interval scheduling

    Ask AI
  2. Q1.2

    In case of CPM, the performance of a specific task is known as

    a)

    dummy

    b)

    event

    c)

    contract

    d)

    activity

    Ask AI
  3. Q1.3

    Military organization is also called as

    a)

    line organization

    b)

    line and staff organization

    c)

    functional organization

    d)

    None of the above

    Ask AI
  4. Q1.4

    Which of the following is incorrect statement?

    a)

    The activity is the time consuming part of a project.

    b)

    The beginning and end of a job, are called events.

    c)

    The activity which consumes maximum time, is called a node.

    d)

    Logically and sequentially connected activities and events form a network.

    Ask AI
  5. Q1.5

    Without affecting the start of succeeding activities, the time by which activity completion time can be delayed, is known as

    a)

    duration

    b)

    interfering float

    c)

    free float

    d)

    total float

    Ask AI
  6. Q1.6

    In bar chart, the various activities of a project, are shown by

    a)

    vertical lines

    b)

    horizontal lines

    c)

    dots

    d)

    crosses

    Ask AI
  7. Q1.7

    The time which is responsible for least possible construction cost of an activity, is

    a)

    normal time

    b)

    crash time

    c)

    standard time

    d)

    slow time

    Ask AI
  8. Q1.8

    If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively

    a)

    3.5 and (5/6)(5/6)

    b)

    5 and (25/36)(25/36)

    c)

    3.5 and (25/36)(25/36)

    d)

    4 and (5/6)(5/6)

    Ask AI
  9. Q1.9

    A critical ratio scheduling

    a)

    determines the status of each activity

    b)

    adjusts automatically changes in activity progress

    c)

    is a dynamic system

    d)

    None of the above

    Ask AI
  10. Q1.10

    A machine costs 20,000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be

    a)

    1,740

    b)

    3,480

    c)

    5,220

    d)

    6,960

    Ask AI

Q.2 Solve both questions :

Ask AI
  1. Q2.1

    Assess the present constructional infrastructure in India. Give the remedial measures keeping in mind the economic feasibility.

    Ask AI

Q.3 Solve this question :

Ask AI
  1. Q3.1

    What is critical path method? Prepare the network as per the data given in the Table 1 and compute in a table their early start, early finish, late start and late finish times. Determine the critical path and find the total float and free float for all the activities:

    Ask AI

Q.4 Solve both questions :

Ask AI
  1. Q4.1

    What do you mean by PERT and what is its significance?

    Ask AI

Q.5 Solve both questions :

Ask AI
  1. Q5.1

    Write the factors to be considered for precast concrete construction. What do you mean by scaffolding?

    Ask AI

Q.6 Solve this question :

Ask AI
  1. Q6.1

    Compare the characteristics and application of the different types of earth excavating equipment. Estimate the output of bulldozer for the following operating conditions: (a) Material - Sandy loam top soil (b) Swell - 25% (c) Haul distance - 45 m (d) Mould board size - 3.0 m long, 1.0 m high (e) Rated mould board capacity - 3 cu.m loose volume (f) Operating factor - 50 min/hr (g) Probable round trip time - 1.87 min.

    Ask AI

Q.7 Solve both questions :

Ask AI
  1. Q7.1

    Explain the application of BIM in project management. What are the safety measures to be considered in the construction site?

    Ask AI

Q.8 Solve both questions :

Ask AI
  1. Q8.1

    Explain the importance of organization in construction activities. What are the methods of scheduling?

    Ask AI

Q.9 Solve both questions :

Ask AI
  1. Q9.1

    What is called liquidated damage? What do you mean by direct cost and indirect cost?

    Ask AI

2022V3101602

B.Tech 6th Semester Exam., 2022

03 Hours70 marks

Instructions

  • The marks are indicated in the right-hand margin.
  • There are NINE questions in this paper.
  • Attempt FIVE questions in all.
  • Question No. 1 is compulsory.
  • Assume any data not given.

Q.1 Choose the correct answer of the following (any seven):

Ask AI
  1. Q1.1

    For establishing and maintaining priorities among the various jobs of a project, the technique is known as

    a)

    critical ratio scheduling

    b)

    event flow scheduling technique

    c)

    slotting technique for scheduling

    d)

    short interval scheduling

    Ask AI
  2. Q1.2

    In case of CPM, the performance of a specific task is known as

    a)

    dummy

    b)

    event

    c)

    contract

    d)

    activity

    Ask AI
  3. Q1.3

    Military organization is also called as

    a)

    line organization

    b)

    line and staff organization

    c)

    functional organization

    d)

    None of the above

    Ask AI
  4. Q1.4

    Which of the following is incorrect statement?

    a)

    The activity is the time consuming part of a project.

    b)

    The beginning and end of a job, are called events.

    c)

    The activity which consumes maximum time, is called a node.

    d)

    Logically and sequentially connected activities and events form a network.

    Ask AI
  5. Q1.5

    Without affecting the start of succeeding activities, the time by which activity completion time can be delayed, is known as

    a)

    duration

    b)

    interfering float

    c)

    free float

    d)

    total float

    Ask AI
  6. Q1.6

    In bar chart, the various activities of a project, are shown by

    a)

    vertical lines

    b)

    horizontal lines

    c)

    dots

    d)

    crosses

    Ask AI
  7. Q1.7

    The time which is responsible for least possible construction cost of an activity, is

    a)

    normal time

    b)

    crash time

    c)

    standard time

    d)

    slow time

    Ask AI
  8. Q1.8

    If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively

    a)

    3.5 and (5/6)(5/6)

    b)

    5 and (25/36)(25/36)

    c)

    3.5 and (25/36)(25/36)

    d)

    4 and (5/6)(5/6)

    Ask AI
  9. Q1.9

    A critical ratio scheduling

    a)

    determines the status of each activity

    b)

    adjusts automatically changes in activity progress

    c)

    is a dynamic system

    d)

    None of the above

    Ask AI
  10. Q1.10

    A machine costs 20,000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be

    a)

    1,740

    b)

    3,480

    c)

    5,220

    d)

    6,960

    Ask AI

Q.2 Solve both questions :

Ask AI
  1. Q2.1

    Assess the present constructional infrastructure in India. Give the remedial measures keeping in mind the economic feasibility.

    Ask AI

Q.3 Solve this question :

Ask AI
  1. Q3.1

    What is critical path method? Prepare the network as per the data given in the Table 1 and compute in a table their early start, early finish, late start and late finish times. Determine the critical path and find the total float and free float for all the activities:

    Ask AI

Q.4 Solve both questions :

Ask AI
  1. Q4.1

    What do you mean by PERT and what is its significance?

    Ask AI

Q.5 Solve both questions :

Ask AI
  1. Q5.1

    Write the factors to be considered for precast concrete construction. What do you mean by scaffolding?

    Ask AI

Q.6 Solve this question :

Ask AI
  1. Q6.1

    Compare the characteristics and application of the different types of earth excavating equipment. Estimate the output of bulldozer for the following operating conditions: (a) Material - Sandy loam top soil (b) Swell - 25% (c) Haul distance - 45 m (d) Mould board size - 3.0 m long, 1.0 m high (e) Rated mould board capacity - 3 cu.m loose volume (f) Operating factor - 50 min/hr (g) Probable round trip time - 1.87 min.

    Ask AI

Q.7 Solve both questions :

Ask AI
  1. Q7.1

    Explain the application of BIM in project management. What are the safety measures to be considered in the construction site?

    Ask AI

Q.8 Solve both questions :

Ask AI
  1. Q8.1

    Explain the importance of organization in construction activities. What are the methods of scheduling?

    Ask AI

Q.9 Solve both questions :

Ask AI
  1. Q9.1

    What is called liquidated damage? What do you mean by direct cost and indirect cost?

    Ask AI

2022V4101602

B.Tech 6th Semester Exam., 2022

03 Hours70 marks

Instructions

  • The marks are indicated in the right-hand margin.
  • There are NINE questions in this paper.
  • Attempt FIVE questions in all.
  • Question No. 1 is compulsory.
  • Assume any data not given.

Q.1 Choose the correct answer of the following (any seven):

Ask AI
  1. Q1.1

    For establishing and maintaining priorities among the various jobs of a project, the technique is known as

    a)

    critical ratio scheduling

    b)

    event flow scheduling technique

    c)

    slotting technique for scheduling

    d)

    short interval scheduling

    Ask AI
  2. Q1.2

    In case of CPM, the performance of a specific task is known as

    a)

    dummy

    b)

    event

    c)

    contract

    d)

    activity

    Ask AI
  3. Q1.3

    Military organization is also called as

    a)

    line organization

    b)

    line and staff organization

    c)

    functional organization

    d)

    None of the above

    Ask AI
  4. Q1.4

    Which of the following is incorrect statement?

    a)

    The activity is the time consuming part of a project.

    b)

    The beginning and end of a job, are called events.

    c)

    The activity which consumes maximum time, is called a node.

    d)

    Logically and sequentially connected activities and events form a network.

    Ask AI
  5. Q1.5

    Without affecting the start of succeeding activities, the time by which activity completion time can be delayed, is known as

    a)

    duration

    b)

    interfering float

    c)

    free float

    d)

    total float

    Ask AI
  6. Q1.6

    In bar chart, the various activities of a project, are shown by

    a)

    vertical lines

    b)

    horizontal lines

    c)

    dots

    d)

    crosses

    Ask AI
  7. Q1.7

    The time which is responsible for least possible construction cost of an activity, is

    a)

    normal time

    b)

    crash time

    c)

    standard time

    d)

    slow time

    Ask AI
  8. Q1.8

    If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively

    a)

    3.5 and (5/6)(5/6)

    b)

    5 and (25/36)(25/36)

    c)

    3.5 and (25/36)(25/36)

    d)

    4 and (5/6)(5/6)

    Ask AI
  9. Q1.9

    A critical ratio scheduling

    a)

    determines the status of each activity

    b)

    adjusts automatically changes in activity progress

    c)

    is a dynamic system

    d)

    None of the above

    Ask AI
  10. Q1.10

    A machine costs 20,000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be

    a)

    1,740

    b)

    3,480

    c)

    5,220

    d)

    6,960

    Ask AI

Q.2 Solve both questions :

Ask AI
  1. Q2.1

    Assess the present constructional infrastructure in India. Give the remedial measures keeping in mind the economic feasibility.

    Categorize the different construction works. Explain the different criteria of selection of site for a project.

    Ask AI

Q.3 Solve this question :

Ask AI
  1. Q3.1

    What is critical path method? Prepare the network as per the data given in the Table 1 and compute in a table their early start, early finish, late start and late finish times. Determine the critical path and find the total float and free float for all the activities:

    Activity Duration (days) Activity Duration (days)
    1-2 8 4-7 0
    1-3 10 5-6 4
    1-4 5 5-7 3
    2-7 6 5-8 6
    3-4 3 6-8 5
    4-5 7 7-8 5
    Ask AI

Q.4 Solve both questions :

Ask AI
  1. Q4.1

    What do you mean by PERT and what is its significance?

    As per the given network find the expected time for each of the paths. Also find the critical path as well as the expected time for the project completion.

    Question Diagram
    Ask AI

Q.5 Solve both questions :

Ask AI
  1. Q5.1

    Write the factors to be considered for precast concrete construction. What do you mean by scaffolding?

    A project takes 20 days along the critical path and has a standard deviation of 4 days. What is the probability of completing the project within (a) 20 days, (b) 24 days and (c) 18 days?

    Ask AI

Q.6 Solve this question :

Ask AI
  1. Q6.1

    Compare the characteristics and application of the different types of earth excavating equipment. Estimate the output of bulldozer for the following operating conditions: (a) Material - Sandy loam top soil (b) Swell - 25% (c) Haul distance - 45 m (d) Mould board size - 3.0 m long, 1.0 m high (e) Rated mould board capacity - 3 cu.m loose volume (f) Operating factor - 50 min/hr (g) Probable round trip time - 1.87 min.

    Ask AI

Q.7 Solve both questions :

Ask AI
  1. Q7.1

    Explain the application of BIM in project management. What are the safety measures to be considered in the construction site?

    A target date of completion is to be forecast based on the following information: Item A takes 7 weeks for completion; Item B takes 5 weeks; Item C depends on the completion of both A and B, and requires 3 weeks; Item D follow up of Item C and requires 2 weeks. Prepare a Gantt chart for scheduling the completion date.

    Ask AI

Q.8 Solve both questions :

Ask AI
  1. Q8.1

    Explain the importance of organization in construction activities. What are the methods of scheduling?

    For the construction of a guesthouse, certain activities are to be performed as shown in Table 2. Activities 2 and 3 can be performed simultaneously and can start only when Activity 1 is completed. Activity 4 can start only after Activity 2 ends. Activity 5 cannot begin until activities 2 and 3 are completed. Activity 6 can start only after Activities 4 and 5 are completed. Activity 7 is the last activity and this can commence only after the completion of Activity 5. (a) Prepare a bar chart for the project. (b) What is the total time taken for the completion of the project?

    Activity No. Duration (in weeks)
    1 2
    2 3
    3 5
    4 4
    5 2
    6 3
    7 5
    Ask AI

Q.9 Solve both questions :

Ask AI
  1. Q9.1

    What is called liquidated damage? What do you mean by direct cost and indirect cost?

    The following Table 3 gives the data for the duration and costs of each activity of a project network. The indirect cost of the project is 3,000/week. Determine the optimum duration of project and the corresponding minimum cost. Draw the time scaled version of the network:

    Question Diagram
    Activity Normal Duration (week) Normal Cost (Rs) Crash Duration (week) Crash Cost (Rs)
    1-2 6 7,000 3 14,500
    1-3 8 4,000 5 8,500
    2-3 4 6,000 1 9,000
    2-4 5 8,000 3 15,000
    3-4 5 5,000 3 11,000
    Ask AI

2022V5101602

B.Tech 6th Semester Exam., 2022

03 Hours70 marks

Instructions

  • The marks are indicated in the right-hand margin.
  • There are NINE questions in this paper.
  • Attempt FIVE questions in all.
  • Question No. 1 is compulsory.
  • Assume any data not given.

Q.1 Choose the correct answer of the following (any seven):

Ask AI
  1. Q1.1

    For establishing and maintaining priorities among the various jobs of a project, the technique is known as

    a)

    critical ratio scheduling

    b)

    event flow scheduling technique

    c)

    slotting technique for scheduling

    d)

    short interval scheduling

    Ask AI
  2. Q1.2

    In case of CPM, the performance of a specific task is known as

    a)

    dummy

    b)

    event

    c)

    contract

    d)

    activity

    Ask AI
  3. Q1.3

    Military organization is also called as

    a)

    line organization

    b)

    line and staff organization

    c)

    functional organization

    d)

    None of the above

    Ask AI
  4. Q1.4

    Which of the following is incorrect statement?

    a)

    The activity is the time consuming part of a project.

    b)

    The beginning and end of a job, are called events.

    c)

    The activity which consumes maximum time, is called a node.

    d)

    Logically and sequentially connected activities and events form a network.

    Ask AI
  5. Q1.5

    Without affecting the start of succeeding activities, the time by which activity completion time can be delayed, is known as

    a)

    duration

    b)

    interfering float

    c)

    free float

    d)

    total float

    Ask AI
  6. Q1.6

    In bar chart, the various activities of a project, are shown by

    a)

    vertical lines

    b)

    horizontal lines

    c)

    dots

    d)

    crosses

    Ask AI
  7. Q1.7

    The time which is responsible for least possible construction cost of an activity, is

    a)

    normal time

    b)

    crash time

    c)

    standard time

    d)

    slow time

    Ask AI
  8. Q1.8

    If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively

    a)

    3.5 and (5/6)(5/6)

    b)

    5 and (25/36)(25/36)

    c)

    3.5 and (25/36)(25/36)

    d)

    4 and (5/6)(5/6)

    Ask AI
  9. Q1.9

    A critical ratio scheduling

    a)

    determines the status of each activity

    b)

    adjusts automatically changes in activity progress

    c)

    is a dynamic system

    d)

    None of the above

    Ask AI
  10. Q1.10

    A machine costs 20,000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be

    a)

    1,740

    b)

    3,480

    c)

    5,220

    d)

    6,960

    Ask AI

Q.2 Solve both questions :

Ask AI
  1. Q2.1

    Assess the present constructional infrastructure in India. Give the remedial measures keeping in mind the economic feasibility.

    Categorize the different construction works. Explain the different criteria of selection of site for a project.

    Ask AI

Q.3 Solve this question :

Ask AI
  1. Q3.1

    What is critical path method? Prepare the network as per the data given in the Table 1 and compute in a table their early start, early finish, late start and late finish times. Determine the critical path and find the total float and free float for all the activities:

    Activity Duration (days) Activity Duration (days)
    1-2 8 4-7 0
    1-3 10 5-6 4
    1-4 5 5-7 3
    2-7 6 5-8 6
    3-4 3 6-8 5
    4-5 7 7-8 5
    Ask AI

Q.4 Solve both questions :

Ask AI
  1. Q4.1

    What do you mean by PERT and what is its significance?

    As per the given network find the expected time for each of the paths. Also find the critical path as well as the expected time for the project completion.

    Question Diagram
    Ask AI

Q.5 Solve both questions :

Ask AI
  1. Q5.1

    Write the factors to be considered for precast concrete construction. What do you mean by scaffolding?

    A project takes 20 days along the critical path and has a standard deviation of 4 days. What is the probability of completing the project within (a) 20 days, (b) 24 days and (c) 18 days?

    Ask AI

Q.6 Solve this question :

Ask AI
  1. Q6.1

    Compare the characteristics and application of the different types of earth excavating equipment. Estimate the output of bulldozer for the following operating conditions: (a) Material - Sandy loam top soil (b) Swell - 25% (c) Haul distance - 45 m (d) Mould board size - 3.0 m long, 1.0 m high (e) Rated mould board capacity - 3 cu.m loose volume (f) Operating factor - 50 min/hr (g) Probable round trip time - 1.87 min.

    Ask AI

Q.7 Solve both questions :

Ask AI
  1. Q7.1

    Explain the application of BIM in project management. What are the safety measures to be considered in the construction site?

    A target date of completion is to be forecast based on the following information: Item A takes 7 weeks for completion; Item B takes 5 weeks; Item C depends on the completion of both A and B, and requires 3 weeks; Item D follow up of Item C and requires 2 weeks. Prepare a Gantt chart for scheduling the completion date.

    Ask AI

Q.8 Solve both questions :

Ask AI
  1. Q8.1

    Explain the importance of organization in construction activities. What are the methods of scheduling?

    For the construction of a guesthouse, certain activities are to be performed as shown in Table 2. Activities 2 and 3 can be performed simultaneously and can start only when Activity 1 is completed. Activity 4 can start only after Activity 2 ends. Activity 5 cannot begin until activities 2 and 3 are completed. Activity 6 can start only after Activities 4 and 5 are completed. Activity 7 is the last activity and this can commence only after the completion of Activity 5. (a) Prepare a bar chart for the project. (b) What is the total time taken for the completion of the project?

    Activity No. Duration (in weeks)
    1 2
    2 3
    3 5
    4 4
    5 2
    6 3
    7 5
    Ask AI

Q.9 Solve both questions :

Ask AI
  1. Q9.1

    What is called liquidated damage? What do you mean by direct cost and indirect cost?

    The following Table 3 gives the data for the duration and costs of each activity of a project network. The indirect cost of the project is 3,000/week. Determine the optimum duration of project and the corresponding minimum cost. Draw the time scaled version of the network:

    Question Diagram
    Activity Normal Duration (week) Normal Cost (Rs) Crash Duration (week) Crash Cost (Rs)
    1-2 6 7,000 3 14,500
    1-3 8 4,000 5 8,500
    2-3 4 6,000 1 9,000
    2-4 5 8,000 3 15,000
    3-4 5 5,000 3 11,000